An operations Management project on MS Project

See the MS Project Exercise for the questions and information about this assignment. Here is the link to the assignment description:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

https://drive.google.com/file/d/1KEJc5EgtMM3oDGB3cD7-7395OKMOnsOy/view?usp=sharing

Students will need to submit (1) MS Project file and (2) a PPT file that includes the screenshots of the Gantt Chart, Network Diagram, Resource Sheet, and Scheduling. At the end of the PPT file, add a slide that reflects what you learned from this exercise. Make sure to address the following restrictions when completing the project.

Schedule the project from the project start date• Five engineers and 15 technicians are available for the project’s duration.• Engineers and technicians are paid $100/hour and $35/hour, respectively.• Engineers’ and Technicians’ hourly rates will be increased to $135 and $45, respectively, in two months Operations Management
MS Project Management
MICROSOFT PROJECT EXERCISE
An aerospace company has received a contract from NASA for the final
assembly of a space module for an upcoming mission. The Project Manager has
identified two types of critical resources, engineers and technicians that are
needed in the project. Following table lists the project tasks, their precedence
relationships, durations, material cost and resource requirements. The
indicated resources are needed for the duration of each task. For example 3
engineers and 7 technicians are needed during the 30 days of task time for Task
A and a half time engineer and 1 technician are needed for the 30 days of task
duration for Task C.
Task
Task Definition
Duration Predecessors Material Engineers Technicians
Label
(Days)
Cost
Required Required
A
Construct Shell of Module
30
$35,000
3
7
B
Procure Life Support System
15
$50,000
0.5
0
and Experimentation Package
C
Procure Components of
30
$80,000
0.5
1
Control and Navigational
System
D
E
F
G
H
I
J
K
Wire Module
Assemble Control and
Navigational System
Preliminary Test of Life
Support System
Install Life Support in Module
Install Experimentation
Package in Module
Preliminary Test of Control
and Navigational System
Install Control and
Navigational System in
Module
Final Testing and Debugging
3
7
A
C
$4,500
$1,500
3
2
5
6
2
B
$1,500
1
3
5
3
D, F
D, F
$1,000
$1,200
1
1
5
4
4
E, F
$1,800
1
3
10
H, I
$3,000
2
6
8
G, J
$4,800
2
5
• Schedule the project from the project start date
• Five engineers and 15 technicians are available for the duration of the project.
• Engineers and technicians are paid at the rate of $100/hour and $35/hour,
respectively.
• Engineers’ and Technicians hourly rate will be increased to $135, and $45,
respectively, in two months.
Instructor: Dr. James J. Roh
1
Assignment 2: MS Project
See the instruction below and complete the assignment using MS Project. An example
and explanation for MS Project is available in the video clip under Module 6. Upload MS
Project Management file.
MICROSOFT PROJECT EXERCISE
An aerospace company has received a contract from NASA for the final assembly of a
space module for an upcoming mission. The Project Manager has identified two types of
critical resources, engineers and technicians that are needed in the project. Following
table lists the project tasks, their precedence relationships, durations, material cost and
resource requirements. The indicated resources are needed for the duration of each
ask.
For example, 3 engineers and 7 technicians are needed during the 30 days of task time
for Task A and a half time engineer and 1 technician are needed for the 30 days of task
duration for Task C.
Task
Duration
Material Engineers Technicians
Task Definition
Predecessors
Label
(Days)
Cost
Required
Required
A
B
C
D
E
F
G
H
I
Construct Shell of
Module
Procure Life Support
System and
Experimentation
Package
Procure Components
of Control and
Navigational System
Wire Module
Assemble Control
and Navigational
System
Preliminary Test of
Life Support System
Install Life Support
in Module
Install
Experimentation
Package in Module
Preliminary Test of
Control and
Navigational System
30

$35,000
3
7
15

$50,000
0.5
0
30

$80,000
0.5
1
3
A
$4,500
3
5
7
C
$1,500
2
6
2
B
$1,500
1
3
5
D, F
$1,000
1
5
3
D, F
$1,200
1
4
4
E, F
$1,800
1
3
J
Install Control and
Navigational System
in Module
10
H, I
$3,000
2
6
K
Final Testing and
Debugging
8
G, J
$4,800
2
5
Schedule the project from the project start date



Five engineers and 15 technicians are available for the duration of the
project.
Engineers and technicians are paid at the rate of $100/hour and $35/hour,
respectively.
Engineers’ and Technicians hourly rate will be increased to $135, and $45,
respectively, in two months.
Before completing the exercise, you may want to watch my lecture on MS Project found
in the media gallery.
To get an access to MS Project, you will need to use Rowan Cloud. If you are unsure of
how to use Rowan Cloud, please watch the video clip I posted.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
Are you stuck with your online class?
Get help from our team of writers!

Order your essay today and save 20% with the discount code RAPID